Back to Projects

Construction of water supply pipeline (Taleghan)

From Taleghan to Robat Karim , section II- Construction Activities

48- water supply pipeline from Taleghan to Robat Karim- 01

 

Construction activities consisting of:

  • Installation of 72″ steel pipeline (26 Km)
  • Removal of rust and hot insulation
  • Installation of 16 Block Valves (64″)
  • Installation of 41 Vent and Drain Valves (8″)
  • Internal coating of pipeline by cement mortar
  • Other construction activities such as channel, back- filling, major and minor river crossing and abou 60 concrete pit for valves and hydro static tests

 

 

48- water supply pipeline from Taleghan to Robat Karim- 02

 

 

 

 

 

Location